Measures actual time from raw material to finished product. Indicates process efficiency and identifies bottlenecks.

Trin-for-trin guide

  1. 1Timestamp order entry through completion
  2. 2Account for wait time and processing time
  3. 3Analyze by step to find delays
  4. 4Compare to takt time
  5. 5Identify improvement opportunities

Løste eksempler

Input
100 units, 8hrs
Resultat
4.8 min/unit

Almindelige fejl at undgå

  • Including non-productive time in cycle time
  • Not separating by shift or day of week

Ofte stillede spørgsmål

Should cycle time equal takt time?

Ideally cycle time equals or is less than takt time; if greater, production falls behind.

How much waste is typical?

Often 50-90% of cycle time is waiting, not processing; opportunities exist in most processes.