Calculates the maximum time allowed per unit to meet production targets. Sets the pace for production planning.
Fórmula
Formula: takt time = available time ÷ target units
Guía paso a paso
- 1Available production time per day (minutes)
- 2Daily production target (units)
- 3Formula: takt time = available time ÷ target units
- 4One unit must complete in less than takt time
Ejemplos resueltos
Entrada
480min/day, 100u
Resultado
4.8 min/unit
Errores comunes a evitar
- ✕Confusing takt time (pace) with cycle time (actual)
- ✕Not adjusting for breaks and changeovers
Preguntas frecuentes
Why is takt time important?
Provides production target pace; identifies if current speed can meet demand.
How do I reduce takt time?
Increase available time (extend hours), or reduce target (fewer units needed).