Measures project progress by comparing work completed to budget spent. Identifies if projects are ahead, on-track, or behind schedule/budget.
सूत्र
SPI = EV ÷ PV (schedule performance)
- SPI
- EV ÷ PV (schedule performance) — EV ÷ PV (schedule performance)
- EV
- EV value — Variable used in the calculation
- PV
- PV value — Variable used in the calculation
चरण-दर-चरण मार्गदर्शिका
- 1Planned Value (PV): budgeted cost for work scheduled
- 2Earned Value (EV): budgeted cost of completed work
- 3Actual Cost (AC): real cost spent
- 4SPI = EV ÷ PV (schedule performance)
- 5CPI = EV ÷ AC (cost performance)
हल किए गए उदाहरण
इनपुट
80% done, $1M
परिणाम
$800k EV
सामान्य गलतियां जिनसे बचना है
- ✕Not updating progress regularly (weekly minimum)
- ✕Misaligning earned value with actual completion percentage
अक्सर पूछे जाने वाले प्रश्न
What do SPI and CPI indicate?
SPI >1 ahead schedule, <1 behind; CPI >1 under budget, <1 over budget.
How do I forecast final cost?
Estimate at Completion (EAC) = BAC ÷ CPI; shows final cost if current performance continues.