Measures the amount of work completed in a sprint in story points. Predicts capacity and enables accurate release planning.
चरण-दर-चरण मार्गदर्शिका
- 1Estimate story points per task (Fibonacci: 1, 2, 3, 5, 8)
- 2Complete sprint (1-2 weeks)
- 3Sum story points of completed items
- 4Track velocity over multiple sprints
- 5Use average for planning
हल किए गए उदाहरण
इनपुट
50pts/2wk
परिणाम
25pts/week
सामान्य गलतियां जिनसे बचना है
- ✕Including incomplete items in velocity
- ✕Adding scope mid-sprint without removing items
अक्सर पूछे जाने वाले प्रश्न
What velocity indicates maturity?
New teams: 20-40 points; established: 50-100; high-performance: 100-150+ depending on team size.
What affects velocity?
Team composition, interruptions, estimation accuracy, and technical debt.