Measures actual time from raw material to finished product. Indicates process efficiency and identifies bottlenecks.

Guida passo passo

  1. 1Timestamp order entry through completion
  2. 2Account for wait time and processing time
  3. 3Analyze by step to find delays
  4. 4Compare to takt time
  5. 5Identify improvement opportunities

Esempi risolti

Ingresso
100 units, 8hrs
Risultato
4.8 min/unit

Errori comuni da evitare

  • Including non-productive time in cycle time
  • Not separating by shift or day of week

Domande frequenti

Should cycle time equal takt time?

Ideally cycle time equals or is less than takt time; if greater, production falls behind.

How much waste is typical?

Often 50-90% of cycle time is waiting, not processing; opportunities exist in most processes.