Overall Equipment Effectiveness measures equipment performance combining availability, performance, and quality. Identifies improvement opportunities.

Formula

Availability = actual run time ÷ planned run time

Guida passo passo

  1. 1Availability = actual run time ÷ planned run time
  2. 2Performance = actual output ÷ theoretical output
  3. 3Quality = good units ÷ total units
  4. 4OEE = Availability × Performance × Quality

Esempi risolti

Ingresso
80% avail, 95% perf
Risultato
72.2% OEE

Errori comuni da evitare

  • Not including planned downtime in availability calculation
  • Using unrealistic theoretical maximums

Domande frequenti

What's good OEE?

Below 65% poor, 65-85% acceptable, 85%+ excellent; world-class manufacturers achieve 90%+.

What causes low OEE?

Equipment downtime, slow running speed, defects; typically 40% availability, 5% performance, 5% quality loss.