Concrete is made of cement, sand, gravel, and water. Calculating the volume before ordering or mixing prevents expensive over-ordering or frustrating shortages. Volume is always measured in cubic feet or cubic yards.

Stapsgewijze handleiding

  1. 1Measure length, width, and depth of the pour in feet
  2. 2Volume (cubic feet) = length × width × depth
  3. 3Cubic yards = cubic feet ÷ 27
  4. 4Add 5–10% waste factor for form overruns and spillage

Uitgewerkte voorbeelden

Invoer
20×15 ft slab, 4 in (0.33 ft) deep
Resultaat
3.33 yd³ + 10% = 3.67 yd³
20×15×0.33=99 ft³÷27=3.67
Invoer
Footing: 40×1×2 ft
Resultaat
2.96 yd³
80 ft³÷27