learn.howToCalculate

learn.whatIsHeading

Concrete is made of cement, sand, gravel, and water. Calculating the volume before ordering or mixing prevents expensive over-ordering or frustrating shortages. Volume is always measured in cubic feet or cubic yards.

Przewodnik krok po kroku

  1. 1Measure length, width, and depth of the pour in feet
  2. 2Volume (cubic feet) = length × width × depth
  3. 3Cubic yards = cubic feet ÷ 27
  4. 4Add 5–10% waste factor for form overruns and spillage

Rozwiązane przykłady

Wejście
20×15 ft slab, 4 in (0.33 ft) deep
Wynik
3.33 yd³ + 10% = 3.67 yd³
20×15×0.33=99 ft³÷27=3.67
Wejście
Footing: 40×1×2 ft
Wynik
2.96 yd³
80 ft³÷27