Overall Equipment Effectiveness measures equipment performance combining availability, performance, and quality. Identifies improvement opportunities.
Wzór
Availability = actual run time ÷ planned run time
Przewodnik krok po kroku
- 1Availability = actual run time ÷ planned run time
- 2Performance = actual output ÷ theoretical output
- 3Quality = good units ÷ total units
- 4OEE = Availability × Performance × Quality
Rozwiązane przykłady
Wejście
80% avail, 95% perf
Wynik
72.2% OEE
Częste błędy do unikania
- ✕Not including planned downtime in availability calculation
- ✕Using unrealistic theoretical maximums
Często zadawane pytania
What's good OEE?
Below 65% poor, 65-85% acceptable, 85%+ excellent; world-class manufacturers achieve 90%+.
What causes low OEE?
Equipment downtime, slow running speed, defects; typically 40% availability, 5% performance, 5% quality loss.