🧠Mixed10 questions
Critical Path Calculator Quiz
Test your understanding of critical path calculator with randomized questions. Each attempt generates new numbers for a fresh challenge.
Pule a matemática - use a calculadora
Abrir Calculadora1 / 10
Task P is a predecessor to Task S. Task S has a Late Start (LS) of 23 days. Assuming a Finish-to-Start (FS) dependency, what is the Late Finish (LF) of Task P?