Earned Valueని ఎలా లెక్కించాలి

Earned Value అంటే ఏమిటి?

Measures project progress by comparing work completed to budget spent. Identifies if projects are ahead, on-track, or behind schedule/budget.

సూత్రం

SPI = EV ÷ PV (schedule performance)
SPI
EV ÷ PV (schedule performance) — EV ÷ PV (schedule performance)
EV
EV value — Variable used in the calculation
PV
PV value — Variable used in the calculation

దశల వారీ గైడ్

  1. 1Planned Value (PV): budgeted cost for work scheduled
  2. 2Earned Value (EV): budgeted cost of completed work
  3. 3Actual Cost (AC): real cost spent
  4. 4SPI = EV ÷ PV (schedule performance)
  5. 5CPI = EV ÷ AC (cost performance)

పరిష్కరించిన ఉదాహరణలు

ఇన్పుట్
80% done, $1M
ఫలితం
$800k EV

నివారించాల్సిన సాధారణ తప్పులు

  • Not updating progress regularly (weekly minimum)
  • Misaligning earned value with actual completion percentage

తరచుగా అడిగే ప్రశ్నలు

What do SPI and CPI indicate?

SPI >1 ahead schedule, <1 behind; CPI >1 under budget, <1 over budget.

How do I forecast final cost?

Estimate at Completion (EAC) = BAC ÷ CPI; shows final cost if current performance continues.

లెక్కించడానికి సిద్ధంగా ఉన్నారా? ఉచిత Earned Value కాలిక్యులేటర్‌ని ప్రయత్నించండి

దీన్ని మీరే ప్రయత్నించండి →