Ordering the right amount of concrete can be the difference between a smooth pour and an expensive mistake. Too little and you're mixing emergency bags in a panic. Too much and you've wasted money. Here's how to calculate exactly what you need.

The Core Formula

Concrete volume is calculated in cubic metres (m³) or cubic yards (yd³):

Volume = Length × Width × Depth

All measurements must be in the same unit before multiplying.

Calculating for a Concrete Slab

Example: A patio slab, 4m × 3m, 100mm thick.

Convert depth to metres: 100 mm = 0.1 m

Volume = 4 × 3 × 0.1 = 1.2 m³

Add 5–10% for waste and spillage:

1.2 × 1.1 = 1.32 m³ (with 10% added)

Order 1.4 m³ to be safe.

Quick Reference: Common Depths

ApplicationTypical depth
Path (foot traffic)75–100 mm
Domestic patio100 mm
Driveway (cars)100–150 mm
Garage floor100–150 mm
Lorry/heavy traffic150–200 mm
Foundation strip (small building)150–225 mm
Shed base75–100 mm

Converting to Cubic Yards

For US projects:

1 cubic metre = 1.308 cubic yards
1 cubic yard = 0.765 cubic metres

Example: 1.32 m³ × 1.308 = 1.73 cubic yards

Calculating How Many Bags You Need

Ready-mix bags come in different sizes. Most commonly:

Bag sizeVolume of concrete
25 kg~0.012 m³
20 kg~0.009 m³
40 lb~0.011 m³
60 lb~0.017 m³
80 lb~0.022 m³

Formula:

Bags needed = Volume (m³) / Volume per bag

Example: 1.32 m³ ÷ 0.012 m³ per 25 kg bag = 110 bags

For larger projects, ready-mixed concrete delivered by truck is far more economical.

Ready-Mix vs Bagged Concrete

Ready-mixBagged
Min orderUsually 0.5–1 m³Any amount
Best for>0.5 m³Small repairs, under 0.3 m³
Cost per m³Lower (£80–130)Higher (£150–250 in bags)
QualityConsistentVariable by mixing
LabourLess mixing workMore mixing work

Rule of thumb: For anything larger than a small shed base or garden step, get ready-mix delivered.

Volume for Other Shapes

Circular Slab (Pond base, round patio)

Volume = π × radius² × depth

Example: Circular slab, 3m diameter, 100mm thick:

Radius = 1.5m
Volume = 3.14159 × 1.5² × 0.1 = 3.14159 × 2.25 × 0.1 = 0.707 m³

Footing (Rectangular trench)

Volume = Length × Width × Depth

Example: Strip foundation, 8m long, 600mm wide, 300mm deep:

Volume = 8 × 0.6 × 0.3 = 1.44 m³

Column/Post Hole

Volume = π × radius² × depth

Example: Post hole, 300mm diameter, 600mm deep:

Radius = 0.15m
Volume = 3.14159 × 0.15² × 0.6 = 3.14159 × 0.0225 × 0.6 = 0.0424 m³

For 6 post holes: 0.0424 × 6 = 0.255 m³ (about 22 × 25 kg bags)

Multiple Areas

If you're pouring a driveway with different depths or an L-shaped area, calculate each section separately and add them:

Total volume = Area 1 + Area 2 + Area 3...

Mix Ratios for DIY Concrete

If mixing by hand (for small jobs only):

Mix (cement:sand:aggregate)Use
1:2:3General purpose, foundations
1:1.5:2.5Higher strength slabs
1:3:6Mass fill, less strength needed

Water ratio: aim for about 0.5 parts water per part cement. Too much water weakens concrete significantly.

Finishing Tips

  • Always add 10% waste to your calculated volume
  • Wet the ground before pouring to prevent the earth absorbing water from the concrete
  • Cure properly — cover with polythene for 3–7 days; don't allow to dry too fast
  • Avoid freezing temperatures — concrete should not be poured below 4°C without precautions

Read Next