Identifies the longest sequence of dependent tasks determining minimum project duration. Changes to critical tasks directly impact completion date.

Hướng dẫn từng bước

  1. 1List all project tasks and dependencies
  2. 2Calculate duration for each task
  3. 3Find all paths through tasks
  4. 4Identify longest path (critical path)
  5. 5Monitor critical tasks closely

Ví dụ có lời giải

đầu vào
A→B→C 12days
Kết quả
12 day min

Lỗi thường gặp cần tránh

  • Not identifying all dependencies
  • Assuming adding resources to critical path always helps

Câu hỏi thường gặp

Why focus on critical path?

Delays on critical tasks delay entire project; non-critical tasks have flexibility.

How do I reduce project duration?

Focus on critical path: parallelize tasks, reduce scope, add resources, reduce dependencies.